HANFORD ENERGY CENTRE, STOKE-ON-TRENT

WATKINS MECHANICAL ON BEHALF OF SSE

 

BACKGROUND

The Hanford Energy Centre will ultimately become the back-up energy centre for the Stoke-on-Trent Heat Network (STHN) and is being developed by SSE, with support from Stoke-on-Trent City Council, as part of the wider district heating network programme.

The buried heat network, also being developed by SSE, will utilise heat recovered from a proposed Energy Recovery Facility (ERF) at Hanford, directly adjacent to the new Energy Centre. The ERF is expected to become operational in 2031 and connect to the district heat network at the same time.

In the intervening period, the Hanford Energy Centre will provide the initial heat source from 2030, supplying a range of buildings across the city, including educational, local authority and NHS connections.

OUR ROLE

Following completion of the RIBA Stage 3 design for the buried heat network and the Squires View Energy Centre in Stoke, d3associates was appointed by Watkins, the Design and Build Contractor, to develop the Hanford Energy Centre design to RIBA Stage 3, including support with the planning application process.

As Lead Designer and Architect, d3associates coordinated the range of disciplines required to deliver the RIBA Stage 3 design, including MEP, plant design, civil and structural engineering and fire engineering. This resulted in a fully coordinated design that met the original project brief.

The team also worked closely with the client-appointed Planning Consultant on a range of planning reports and related tasks, including the planning drawing package and Design and Access Statement, ensuring the design and planning requirements were developed together.

d3associates’ experience in district heating network design was particularly valuable in developing the Energy Centre around the operational requirements of the wider network. Having also delivered the buried network design for Stoke, the team had a clear understanding of how the Energy Centre needed to integrate with the network as a whole.

To help manage project risk, d3associates also coordinated a range of additional services through its partner network, including Stage 1 and 2 ground investigations and arboricultural assessments.

THE OUTCOME

The Energy Centre was designed to accommodate the district heating network’s primary generation plant, including the main heat source, thermal storage and supporting infrastructure. However, the project presented a number of challenges, particularly around the site’s limited footprint and ground conditions.

The location had to be carefully considered in response to both the spatial constraints and the site’s historical use and associated ground contamination. A series of layouts was developed to make best use of the available space, while swept path analysis was used to accommodate large vehicle movements and ensure provision for the thermal store.

The resulting RIBA Stage 3 design takes the form of a simple, robust cube, with the flue stack positioned towards the right-hand side of the building to give it deliberate prominence. Internally, the layout separates the industrial plant areas from the spaces required for staff and visitors, including welfare, office and meeting facilities.

Alongside space efficiency, the team considered the materiality and construction of the building to ensure the proposed solution was appropriate for its context and practical to deliver. The external material strategy uses a palette of industrial materials in a tripartite arrangement, with the flue element and upper-level cladding sitting above a robust lower-level plinth.

From a plant design perspective, d3associates led the development of a solution capable of meeting the network’s current and future heat demand. The team also played a leading role in developing the control philosophy for both the Energy Centre and wider network.

The project brief presented a number of technical and programme challenges, but through a robust approach to project management, multidisciplinary coordination and close collaboration with Watkins, SSE and the planning consultant, the design was delivered ahead of programme and to the satisfaction of both Watkins and SSE.

As part of the wider scope, d3associates also provided quantity surveying services at RIBA Stages 2 and 3, producing cost plans to support SSE’s commercial modelling, the Green Heat Network Fund (GHNF) funding application and future tendering.